← Back to headlines

Consumer Commission Orders Builder to Refund ₹1.4 Crore with 18% Interest for 12-Year Delay
India's National Consumer Disputes Redressal Commission has ordered a builder to refund ₹1.4 crore with 18% interest due to a 12-year delay in project completion, penalizing the developer for the prolonged wait.
24 Mar, 08:30 — 24 Mar, 08:30
Sources
Showing 1 of 1 sources


