A69 highway concessionaire receives €79 million compensation after construction interruption
The concessionaire Atosca has received 79 million euros in compensation after the construction of the new Toulouse-Castres A69 highway was interrupted by a Toulouse administrative court ruling on February 27, 2025, though work was later authorized to resume in late May.